GARDINER EXPRESSWAY
Project Details
| Description: | Bridge Replacement |
| Location: | Lower Simcoe off ramp. Toronto, Ontario |
| Owner: | City of Toronto |
| General Contractor: | Grascan Construction |
| NRE Role: | Erection |
| Year: | 2017 |
| Tonnage: | ±200 tons |
| Overview: | This project was part of a downtown core re-habilitation, allowing improved traffic flow and enabling additional green space in a tight urban area. Erection of bridge girders in tight Downtown Toronto setting. All erection and detail work was finished in less than a 2-week period. Bearing welding was also completed by NRE. |