Project Details

Description: New trapezoidal box girder bridge over HWY 417.
Location: Arnprior, Ontario
Owner: MTO
General Contractor: Corington Engineering
NRE Role: Erection
Year: 2015
Tonnage: ±577
Overview: New overpass bridge over HWY 417. Phase 1 girders were field spliced in the air utilizing 350 and 400 Ton cranes. Phase 2 girders were erected in 15 minute full closures of active HWY 417 utilizing a 400 Ton crane. Erection was completed over a total of 7 shifts.