CAMPBELL DR. OVERPASS
Project Details
Description: | New trapezoidal box girder bridge over HWY 417. |
Location: | Arnprior, Ontario |
Owner: | MTO |
General Contractor: | Corington Engineering |
NRE Role: | Erection |
Year: | 2015 |
Tonnage: | ±577 |
Overview: | New overpass bridge over HWY 417. Phase 1 girders were field spliced in the air utilizing 350 and 400 Ton cranes. Phase 2 girders were erected in 15 minute full closures of active HWY 417 utilizing a 400 Ton crane. Erection was completed over a total of 7 shifts. |